Preliminary notification:- Under Section 11 (1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013) (No. 30 of 2013)

Preliminary notification:- Under Section 11 (1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013) (No. 30 of 2013)
Title Description Start Date End Date File
Preliminary notification:- Under Section 11 (1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013) (No. 30 of 2013)

According to the provisions of sub-section (1) of Section 11 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, the persons related to the details of the land shown in Schedule (2) are informed to the effect that the State Government I hereby authorize the officer mentioned in column 5 of Schedule (1) to exercise the powers conferred by the said section 12 in respect of the said land.

Schedule 1) :-

1. District: Khargone

2. Tehsil: Gogawan

3. Village / Town: Mohammadpur

4. Total area of land to be acquired (in ha): 0.440

5. Authorized Officer under Section-12: Executive Engineer Narmada Development Division No. 18 Khargone

6. Description of public purpose: “For the construction of pump house 01 and other works under Bistan lift irrigation scheme”

 

Schedule (2) :-

Details of affected private land of village- Mohammadpur for construction of Pump House 01 and other works under Bistan Lift Irrigation Project:-

Survey Number: 309/456/3

Total area of land to be acquired (in ha): 0.440

 

09/01/2023 31/01/2023 View (278 KB)